2018

July

Central i-City is about 90% to its structural completion – Yes! Paintwork of the mall’s façade is ongoing, gradually changing the landscape of the i-City ultrapolis. Stay tuned for your New Everyday Experience!

May

Working relentlessly towards getting our CCC very soon. We are always geared up for site inspections to ensure quality and efficiency prior to site handover to our tenants.

February

Roof truss are being installed for preparation of metal roof covering and progressive construction of external walls for the shopping centre.

2017

November

Up it goes! Construction progress is on its peak for supporting structures of the mall.
Pillar casting for the top level of retail (L4) is in progress.

August

A bird’s eye view of the entire Central i-City’s construction progress since 2015. The construction works are on a positive progress according to schedule.

May

Timbers are placed as bottom formworks as slab for flooring at different levels of the shopping centre.

2016

November

Slab and column works are in progress for three (3) levels of car park bays (B1 – B3) and six (6) levels of retail (LG – L4).

April

Maintain Load Test (MLT) is in progress to test foundation’s strength in preparation for bore piling works.

February

Crawler cranes and bore pile machines are placed at site for the preparation of foundation works.

2015

October

Land clearing has been completed on the 12-acre land from previous debris. Construction site hoarding is in progress to separate construction site and public area for safety purposes.